CEQA exemption: which one fits your project, and how to file it

A project skips CEQA's environmental review when one of three exemptions covers it: a statutory exemption written by the Legislature, a categorical exemption from the 33 classes in CEQA Guidelines §§15301–15333 that no §15300.2 exception rules out, or the common sense exemption in §15061(b)(3). The lead agency decides. Filing a Notice of Exemption cuts the time to sue from 180 days to 35.

Updated November 2026. Statutes, Guidelines, fees and prices were read on November 13, 2026. This is a guide to the rules, not legal advice.

Find yours in five questions

  1. Is it a CEQA project at all? CEQA covers discretionary approvals by California public agencies (Public Resources Code §21080(a)). A ministerial permit, where staff only check fixed standards, is outside it (§21080(b)(1); Guidelines §15268). Accessory dwelling unit permits are approved ministerially by state law (Gov. Code §66317(a)(1)). From January 1, 2027, data center entitlements need CEQA review even where they would be ministerial (PRC §21080.08, SB 887).
  2. Does a statutory exemption fit? Look in Guidelines Article 18 (§§15260–15285) and the newer statutes, such as §21080.66 for infill housing (AB 130, 2025). The §15300.2 exceptions don't apply to statutory exemptions. See the statutory exemptions list and the AB 130 checklist.
  3. Does a categorical class fit? Each class has its own conditions. The most used are Class 1, existing facilities, Class 3, small new structures and Class 32, infill. All 33 are in the table below.
  4. Does an exception rule it out? Six exceptions in §15300.2 can cancel a categorical exemption: a mapped sensitive location, cumulative impact, unusual circumstances, a state scenic highway, a hazardous-waste (Cortese) list site and historical resources. See the exceptions.
  5. Can it be seen with certainty that there is no possibility of a significant effect? Then the common sense exemption may fit, but the agency carries the burden of showing it.

If nothing fits, the next step is an Initial Study, which leads to a Negative Declaration, a Mitigated Negative Declaration or an EIR: what that adds in time and fees. A project consistent with a plan that already had an EIR may use §15183 streamlining instead.

Statutory, categorical or common sense

Sources: Public Resources Code §§21080, 21084; CEQA Guidelines §§15061, 15260–15285, 15300–15333; the two California Supreme Court cases named.
StatutoryCategoricalCommon sense
Who made itThe Legislature, in the Public Resources CodeThe Natural Resources Agency, under PRC §21084, as Guidelines §§15301–15333Guidelines §15061(b)(3): CEQA reaches only activities that can cause a significant effect
Can a §15300.2 exception defeat it?NoYesNot needed: it applies only where no significant effect is possible
Who must prove whatThe project must meet the statute's conditionsThe challenger must show an exception applies (Berkeley Hillside, 2015)The agency must show it with evidence (Muzzy Ranch, 2007)
ExamplesMinisterial permits, emergency repairs, AB 130 infill housing, housing-element rezonings (§21080.085)Repairs and minor additions (Class 1), a few small buildings (Class 3), infill up to 5 acres (Class 32)Actions with no physical effect at all; used sparingly

Ways to find and document a CEQA exemption, compared

Whoever prepares the paperwork, the lead agency decides. The routes differ in cost, speed and evidence.

Prices in US dollars, read from each provider's own page on November 13, 2026. "By quote" means no public price.
RouteCostWhat you getBest forLimits
Lead agency planning staffThe agency's fee. San Francisco's initial fees: $461 for an exemption checklist, $9,257 for an exemption certificate, plus staff time above thatThe determination itself, and the agency's NOE after approvalSimple projects where the agency's own form is the documentFees and queues vary; staff review, they don't build your case
Environmental consultantBy quote, plus the agency's feeExemption memo, technical studies (traffic, noise, air, water quality), NOE draftClass 32, sensitive sites, projects likely to be challengedSlowest and costliest; the agency still decides
Land use attorneyBy engagementAn opinion on the strongest exemption and the litigation riskContested or high-value projectsAdvice, not usually the technical record
ePlanFree to read; $49 for one document's Word file; Pro $99/month; Office $199/monthFour questions; checks CEQAnet, the Cortese list, listed historical resources, scenic highways and CNDDB; drafts an NOE (Appendix E), an exemption memo, a §15300.2 check and a filing checklistAgency staff and applicants who want a cited first draft from four questionsUnsigned drafts, not legal advice; no technical studies; the finder names Classes 1, 2, 3, 4, 11 and 32 and emergency or ministerial work, the rest as "something else"
AEP 2026 CEQA Statute & GuidelinesFree PDF; print $35 ($25 for AEP members)The statute and Guidelines as of January 1, 2026, summaries of 2025 laws and cases, the Appendix E formReading the rules yourselfUnofficial copy; no 2026 laws
AEP CEQA Portal: "CEQA Exemptions"FreeA practitioners' topic paper on how exemptions workLearning the framework2020 update: predates the 2025 statutory exemptions; the old PDF address returns 404, and the Portal has a login
CEQAnetFreeThe State Clearinghouse database of filed notices, NOEs includedSeeing which exemption agencies used for similar projectsAnother project's NOE is precedent, not proof
LCI Site CheckFreeA state map of parcels where housing may qualify for CEQA streamlining or exemptionsScreening housing sitesHousing only; the state says its output is not legal advice
Practical CEQA (Solano Press)$80 paperback, $40 KindleA step-by-step compliance guide, with a 2026 supplementAgency staff learning the process2020 edition plus supplement
CEB CEQA HubBy quote (free trial)A CEQA research platform for attorneys with Solano Press titles and case summariesLaw firms and agency counselBuilt for lawyers; no public price

Where each route wins. The free official sources win on price. A consultant wins when the exemption rests on technical evidence, as Class 32 does, or when a challenge is likely. ePlan wins on speed for the common classes: a cited draft of the notice, memo and exceptions check from four questions, free to read and $49 to download, still reviewed and signed at the agency. Asking planning staff early which exemption they expect is the cheapest step of all.

The 33 categorical exemption classes

Short summaries; each section's full conditions control.

Source: CEQA Guidelines §§15301–15333 (14 CCR), as published in the AEP 2026 edition and on Cornell's LII, read November 13, 2026.
ClassSectionCovers
1§15301Operation, repair, maintenance or minor alteration of existing facilities, with negligible or no expansion of use
2§15302Replacing or rebuilding a structure on the same site, same purpose and capacity
3§15303A few new small structures per parcel; converting small structures
4§15304Minor alterations to land, water or vegetation (e.g. grading on slopes under 10%)
5§15305Minor changes in land use limits on slopes under 20%: lot line adjustments, setback variances
6§15306Data collection, research and resource evaluation
7§15307Regulatory actions to protect natural resources
8§15308Regulatory actions to protect the environment
9§15309Inspections
10§15310Loans for existing structures
11§15311Minor accessory structures at existing commercial, industrial or institutional sites
12§15312Surplus government property sales
13§15313Buying land for wildlife conservation
14§15314Minor additions to existing schools: no more than 25% added student capacity or ten classrooms, whichever is less
15§15315Dividing urbanized land into four or fewer parcels
16§15316Transferring land to create parks
17§15317Open space contracts and easements
18§15318Designating wilderness areas
19§15319Annexing existing facilities and lots for exempt facilities
20§15320Reorganizing local agencies without changing their area
21§15321Enforcement actions by regulatory agencies
22§15322Educational or training programs with no physical change
23§15323Normal operations of existing facilities for public gatherings
24§15324Regulating wages, hours and working conditions
25§15325Transfers of land to preserve open space, habitat or historical resources
26§15326Buying housing for housing assistance programs
27§15327Leasing new facilities
28§15328Small hydroelectric (5 MW or less) at existing dams, canals and pipelines
29§15329Cogeneration (50 MW or less) at existing facilities
30§15330Minor hazardous-substance cleanups costing $1 million or less
31§15331Historical resource restoration consistent with the Secretary of the Interior's Standards
32§15332Infill development up to 5 acres within city limits, meeting five conditions
33§15333Small habitat restoration, up to 5 acres

New statutory exemptions, 2025 and 2026

Details and conditions for each: CEQA statutory exemptions.

Filing the Notice of Exemption and the 35-day clock

  1. Approve first. The notice is filed, if at all, after the project is approved (Guidelines §15062(a)).
  2. Fill in Appendix E: project, location, the exemption with its section or statute, a brief statement of reasons, and the applicant's name (§15062(a)).
  3. File it. A local agency files with the county clerk and, since SB 69 took effect in 2024, with the State Clearinghouse (PRC §21152(b)); a state agency files with the State Clearinghouse (§21108). An applicant may file with the agency's certified determination (§15062(c)(4)).
  4. Pay little. Exempt projects pay no Fish and Wildlife filing fee; the county clerk charges a handling fee (Fish & Game Code §711.4(d)(1), (e) sets $50; counties publish their own schedules).
  5. Count 35 days. Challenges must be filed within 35 days of filing and posting; with no notice, the window is 180 days from approval (PRC §21167(d); Guidelines §15112(c)).

A worked example with every field filled in: how to fill in and file a Notice of Exemption.

Questions people ask

What is exempt from CEQA?

Ministerial approvals fall outside CEQA. Discretionary projects are exempt if a statutory exemption covers them (such as emergency repairs or infill housing under Public Resources Code §21080.66), if they fit one of the 33 categorical classes (Guidelines §§15301–15333) with no §15300.2 exception, or under the common sense exemption (§15061(b)(3)).

What projects require CEQA review?

Discretionary projects that a California public agency carries out or approves, such as rezonings, variances, conditional use permits and tentative maps (Public Resources Code §21080(a)), unless an exemption applies. Without one, the agency starts with an Initial Study.

What are the requirements for the categorical exemption under CEQA Section 15303?

Class 3 allows a few new small structures per legal parcel: one single-family home or a second unit (three homes in urbanized areas), a multifamily structure of up to four units (six in urbanized areas), a commercial building up to 2,500 square feet (larger limits in urbanized areas), utility extensions and accessory structures. The §15300.2 exceptions still apply.

Does CEQA apply to federal projects?

CEQA binds California public agencies, so a purely federal action is reviewed under NEPA instead. When a state or local agency also approves or funds part of the project, CEQA applies to that approval, and Article 14 of the CEQA Guidelines (§§15220–15229) lets agencies use joint or federal documents.

Is there a book that contains the 2026 CEQA Guidelines?

Yes. The Association of Environmental Professionals publishes the 2026 CEQA Statute and Guidelines, current as of January 1, 2026, as a free PDF and in print for $35 ($25 for members). It is an unofficial copy; the official text is on Westlaw's California Code of Regulations site.

Do I have to file a Notice of Exemption?

Usually not. For most exemptions filing is optional, but some statutory exemptions require it (for example PRC §§21080.14, 21080.25, 21080.40 and 21080.66; Guidelines §15062(e)). Filing shortens the time anyone can sue from 180 days to 35 days after filing and posting (Public Resources Code §21167(d); Guidelines §15062(d)). It is filed only after the project is approved.

Who decides whether a project is exempt?

The lead agency (Public Resources Code §21080.1(a)). If staff or another non-elected body made the call, the exemption decision can usually be appealed to the agency's elected body (Guidelines §15061(e)). Consultants, attorneys and software can prepare the paperwork, but none of them decides.

Guides

How we checked

On November 13, 2026 we read every Guidelines section cited here (Cornell's LII and AEP's 2026 edition), the Public Resources Code sections (a public mirror of the Legislature's site), the 2026 bills on CalMatters' Digital Democracy, the Supreme Court's Sunflower Alliance opinion and each route's own price or fee page. No scores or ratings. Found an error? Write to support@winding.ai.

About this site

ceqaexemption.com is published by Winding AI, Inc., the company that makes ePlan, one of the routes compared above. We make money when someone pays ePlan for a download or a plan; we earn nothing from links to anyone else, and links to ePlan carry a tag so it can count visits from here. We wrote it because the top results for "CEQA exemption" are agency PDFs and lists that rarely cover the decision, the exceptions and the filing together. It is not legal advice. Visits are counted with Google Analytics; no ads, and no analytics cookies in the EU, UK or Switzerland.